Current:Home > MarketsMassachusetts budget approval allows utilities to recoup added cost of hydropower corridor -FutureProof Finance
Massachusetts budget approval allows utilities to recoup added cost of hydropower corridor
View
Date:2025-04-15 16:41:26
PORTLAND, Maine (AP) — A budget signed by Massachusetts Gov. Maura Healey this week will allow utilities to raise rates to make up for hundreds of millions of dollars in additional costs to complete a transmission line to bring Canadian hydropower to the New England electricity grid.
The head of Central Maine Power Co.'s corporate parent Avangrid has said the cost of the $1 billion project grew to $1.5 billion as litigation delayed construction and inflation caused prices to creep upward.
Legislation included the supplemental budget adopted Monday allows transmission service agreements to be renegotiated and additional costs to be passed along to Massachusetts ratepayers to cover the added costs.
Avangrid provided the increased costs to Massachusetts’ electricity distribution companies to adjust the rate in the parties’ transmission services agreements, which would be subject to Department of Public Utilities review and approval, Avangrid spokesperson Leo Rosales said in a statement Tuesday.
He praised Healey and lawmakers for taking action to “deliver this critical project and needed clean power to benefit the entire New England region.”
Avangrid partnered with Hydro-Quebec on the New England Clean Energy Connect to supply 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That would be enough electricity to power about a million homes.
The 145-mile (233-kilometer) transmission line will stretch from Lewiston, Maine, to the Canadian border.
It received all regulatory approvals but was plagued by delays, litigation and a referendum in which https://apnews.com/article/election-2021-maine-hydropower-line-54dea1a948e9fc57a667280707cddeb7
It was allowed to move forward after a Maine jury concluded that the developers had a constitutional right to proceed despite the referendum.
Construction resumed in August on a transmission hub that’s critical to the project in Lewiston. But it’s unclear when other work will restart.
Workers had already begun removing trees and setting utility poles on a disputed portion of the project, a new 53-mile (85-kilometer) section cut through the woods in western Maine, before the project was put on hold.
The project was envisioned to meet Massachusetts’ clean energy goals, and the cost is fully borne by ratepayers in that state.
However, supporters say electricity would lower energy costs across New England as well as reduce carbon pollution.
veryGood! (55)
Related
- Former Syrian official arrested in California who oversaw prison charged with torture
- Treat Williams’ Daughter Pens Gut-Wrenching Tribute to Everwood Actor One Month After His Death
- New Wind and Solar Are Cheaper Than the Costs to Operate All But One Coal-Fired Power Plant in the United States
- Robert De Niro's Girlfriend Tiffany Chen Diagnosed With Bell's Palsy After Welcoming Baby Girl
- Don't let hackers fool you with a 'scam
- In Dimock, a Pennsylvania Town Riven by Fracking, Concerns About Ties Between a Judge and a Gas Driller
- Robert De Niro's Girlfriend Tiffany Chen Diagnosed With Bell's Palsy After Welcoming Baby Girl
- This Dime-Sized Battery Is a Step Toward an EV With a 1,000-Mile Range
- Realtor group picks top 10 housing hot spots for 2025: Did your city make the list?
- Scientists Report a Dramatic Drop in the Extent of Antarctic Sea Ice
Ranking
- Nevada attorney general revives 2020 fake electors case
- The Botched Docs Face an Amputation and More Shocking Cases in Grisly Season 8 Trailer
- Outrage over man who desecrated Quran prompts protesters to set Swedish Embassy in Iraq on fire
- Scientists Report a Dramatic Drop in the Extent of Antarctic Sea Ice
- Off the Grid: Sally breaks down USA TODAY's daily crossword puzzle, Triathlon
- Senator’s Bill Would Fine Texans for Multiple Environmental Complaints That Don’t Lead to Enforcement
- Kate Spade 24-Hour Flash Deal: Get a $280 Convertible Crossbody Bag for Just $87
- U.S. cruises to 3-0 win over Vietnam in its Women's World Cup opener
Recommendation
US wholesale inflation accelerated in November in sign that some price pressures remain elevated
Q&A: Cancer Alley Is Real, And Louisiana Officials Helped Create It, Researchers Find
Tearful Damar Hamlin Honors Buffalo Bills Trainers Who Saved His Life at ESPYS 2023
20 Top-Rated Deals Under $25 From Amazon Prime Day 2023
Krispy Kreme offers a free dozen Grinch green doughnuts: When to get the deal
This Winter’s Rain and Snow Won’t be Enough to Pull the West Out of Drought
Kate Spade 24-Hour Flash Deal: Get a $280 Convertible Crossbody Bag for Just $87
ESPYS 2023 Red Carpet Fashion: See Every Look as the Stars Arrive